Lumen Project Day 36 – Starting to get plastered

Lumen Project Day 36

No we are not starting our celebration just yet. The plasterers are now on site and covering the exposed brick work, and tidying up the edges where the demolition took place. The sides of our East window have been complete and the bottom has had battens fitted for the new render.

North and South windows have had the initial layer of plater and the base of the walls are primed for the render.

We have been told that the windows are now being manufactured.

As we are now 5 weeks into the project and hopefully half way there, and all is progressing well.  Keep watching for the new developments.